Construction progress report template

Updated September 10, 2026

Five floors of a concrete frame from outside, timber guardrails along each open slab edge and wrapped material stacked on every level
Photo: Laura Paredis on Pexels

A construction progress report answers one question for somebody who was not there: are we where we said we would be, and if not, by how much. Everything in it either supports that answer or gets cut.

It is a different document from the daily report, which records one day at a time and gets filed. The progress report is a comparison, and it gets read.

The header names the period, not the day

Field What goes in it Example
Project and number The name everyone uses, plus the contract number Northgate Medical Fit-Out, C-2214
Report number and period Sequential, with the dates it covers Progress report 14, Aug 31 to Sep 6, 2026
Prepared by, for Who wrote it and who reads it M. Okafor, GC, for owner and architect
Contract dates Original completion, current forecast Original Nov 20, 2026; forecast Dec 4, 2026
Working days in period Days worked, days lost, why 5 worked, 0 lost

The forecast date belongs on page one of every report, next to the original. Moving it quietly in report 14 and hoping nobody reads report 9 is how a two-week slip becomes a surprise in November. If the forecast moved this period, say so in the same line.

Percent complete has to be tied to something countable

The number that gets argued about is percent complete, and it gets argued about because most reports produce it by feel.

Tie it to units instead. Drywall is sheets hung against sheets in the takeoff. Framing is linear feet of wall. Glazing is units set. Rough-in is fixtures or drops. If you cannot count the thing, count the rooms it is finished in.

Then write the basis down in the report, once, so the figure means the same thing in report 3 and report 14:

Percent complete for each area is hung and finished square footage against the takeoff for that area, excluding punch.

An owner who disagrees with a counted number is disagreeing with the count, which is a short conversation. An owner who disagrees with a feeling has nothing to point at, and that conversation goes on for a week.

Put last period's number beside this one

One table carries most of the report.

Area Scope Last week This week Planned Note
Level 2 east Drywall hang and finish 62% 84% 80% Ahead, second crew added Tuesday
Level 2 west Drywall hang and finish 41% 47% 70% Waiting on above-ceiling electrical signoff
Level 3 MEP rough-in 88% 95% 100% Two medical gas drops remain
Roof Membrane and flashing 100% 100% 100% Complete Aug 28, warranty inspection Sep 11
Exterior Glazing 15% 33% 35% 22 of 66 units set

Three columns do the work. Last week is what makes movement visible, and an area that did not move is the most informative row in the report. Planned is the schedule you are measuring against. The note says why, in one clause, and never more.

The row worth reading twice is Level 2 west: six points of movement against a plan that wanted 29. It is not a disaster, and buried in a paragraph it would be invisible. In the table it is the first thing anyone sees.

Shoot the same frames from the same spots every week

The photo set is what makes the report evidence instead of assertion, and it only works if the frames repeat.

Pick five or six vantage points at the start of the job and mark them. A column line, a stair landing, the same corner of the parking lot. Stand there every week and shoot the same view. Same spot, same direction, roughly the same time of day so the light is comparable.

A reader flipping through fourteen reports sees the west elevation fill in like a flipbook. That comparison is impossible if every week's photos were taken from wherever the photographer happened to be standing.

Six to ten photographs is the right size. Each one gets a caption with the area, the date and what changed since the last report. The photo documentation guide covers how to shoot the individual frames.

The look ahead is two weeks and names who has to move

One week is not enough warning for anyone to act on, and a month of look ahead is fiction. Two weeks.

Period Work planned Depends on
Sep 7 to 13 Level 2 west tape and finish Above-ceiling electrical signoff, requested Sep 2
Sep 7 to 13 Glazing units 23 to 44 Nothing outstanding
Sep 14 to 20 Level 2 east prime and first coat Drywall finish complete
Sep 14 to 20 Level 3 medical gas certification Two drops, then third-party test scheduled

The depends-on column is the reason the section exists. A look ahead that lists work without naming what would stop it is a wish list. Naming the electrical signoff, with the date it was requested, puts the delay in front of the person who can clear it while there is still time to clear it.

Open issues carry a decision date, not a status

An issues list where everything reads "in progress" tells nobody anything.

# Issue Raised Needed by Who decides
22 Above-ceiling electrical inspection not signed Sep 2 Sep 9 AHJ, chased by GC
23 Corridor light fixture substitution, specified unit at 14 weeks Aug 24 Sep 11 Architect and owner
24 Slab depression at Level 2 west, 3/8 inch over 10 feet Sep 4 Sep 12 Structural engineer

Needed by is the field that makes an issue move. It is the date after which the issue costs the schedule, and it is your estimate, not a request. Item 23 has a needed-by that is two weeks earlier than the lead time would suggest, because a decision that lands after the order window has to be made twice.

Carry closed issues for one more report with the resolution and the date, then drop them. A list that only grows gets skimmed.

Write it the day the period closes

The report goes out Monday morning for the week that ended Friday, or it does not get written at all. By Wednesday the photographs are stale, the reason Level 2 west stalled has been half forgotten, and somebody has already asked by email.

On iPhone and iPad, Sitewise covers the walk that produces the photo set. Shoot your repeating vantage points, dictate what changed while you are looking at it (the voice note transcribes on the phone), sketch onto a photo when the change is hard to see, and each capture carries a timestamp and, with location on, a GPS pin. On a Pro iPhone or Pro iPad with a LiDAR scanner, two taps in the camera measure a dimension and print it on the photo, which is how a slab depression gets into the report as a number. Capture works with no signal and syncs later. Pick the frames that go in the report, leave the rest in the project, and export a PDF or DOCX to send. It does not build the schedule or the percent-complete table for you: no scheduling, no budgeting, no cost tracking, no CAD, and no Android or web version.

For the contemporaneous day-by-day record that sits underneath all of this, and that a delay claim is actually built from, use the daily construction report template.

The test of a progress report is whether somebody who has not visited in a month can read it and know which two things to ask about. If every area looks fine and the completion date moved anyway, the report did not do its job.

Questions people ask

What is a construction progress report?
A periodic summary, usually weekly or monthly, written for people who are not on site: the owner, the lender, the architect, sometimes an insurer. It says how much of the work is done, how that compares with where the schedule said you would be, what is blocking the next stage, and it carries photographs as the evidence. It is not the daily report. The daily report is a contemporaneous record of what happened on one day, and it exists mainly for a claim. The progress report is a comparison, and it exists so somebody can decide whether to release money or start worrying about the date.
What should a weekly construction progress report include?
A header naming the reporting period and the report number, percent complete by area with last period's figure beside it, work completed in the period, photographs shot from repeating vantage points so the change is visible, a two-week look ahead naming who has to move, open issues each carrying a decision date, and any days lost to weather or access. Keep it to two or three pages plus photographs. Anything longer stops being read.
Who writes the progress report on a construction project?
Usually the general contractor's project manager or superintendent, sent to the owner and the design team. On projects with a lender draw, an owner's representative or a third-party inspector may write a parallel report that the bank relies on instead. When both exist they are read against each other, which is a good reason to keep your percent-complete figures tied to something countable rather than to a feeling about the week.